Trinity_GrowingOurFuture_logoFINAL-color
PROJECT UPDATES

On May 24, Trinity entered into agreements with contractors covering:

  • Roof Repair. Contracts to repair three of the four sections of roof repairs have been signed. This work is scheduled to begin in early June and to be completed by mid-August before the Preschool fall program begins. The fourth section of roof repairs (the metal roof above the Worship Center) requires a final metal cost estimate, as well as finalizing the amount of damage claim from our insurance carrier. This fourth section of roof also is scheduled to be completed by mid-August.

  • Bathroom Updates. A design committee (Lisa Hardebeck, Mary Hepperly, Christie Tietjen, and Christy Cole, Preschool Director) has been appointed to select the appropriate color schemes and designs for the church bathrooms. Work is expected to begin on this project in June, once materials have been selected and ordered. The project is expected to be completed by mid-August.

  • Upgrades to the Audio and Visual Systems in the Worship Center. This work will begin as soon as hardware is available to complete the project.

 

It is exciting that work is beginning on these Capital Campaign projects! 

Phase 1_060321.jpg
Roof Work_060221 copy.jpg
Roof Work_060221_1 copy.jpg

Roof supplies have arrived and prep work has begun.

Phase 2_060321 .jpg